Lawrence Berkeley National Laboratory masthead LBNL Home A-Z Index U.S. Department of Energy logo Phone Book Jobs Search

RPM

REQUIREMENTS AND POLICIES MANUAL

Search the RPM
 
Home

Advance Payments for Sponsored Research Projects with Non-Federal Sponsors

    Title:

    Advance Payments for Sponsored Research Projects with Non-Federal Sponsors

    Publication date:

    7/28/2016

    Effective date:

    7/28/2016

    BRIEF

    Policy Summary

    When work is performed for non-federal sponsors, sufficient advance funds must be obtained from the sponsor prior to starting work to maintain a positive cash balance during the life of the project. This policy addresses financial processes for estimating the required advance payment for work performed for non-federal sponsors.

    Who Should Read This Policy

    All employees with financial responsibilities for work performed for non-federal sponsors at Berkeley Lab.

    To Read the Full Policy, Go To:

    The POLICY tab on this wiki page

    Contact Information

    • Reimbursable Group Analyst
    • Reimbursable Group Manager

    Title:

    Advance Payments for Sponsored Research Projects with Non-Federal Sponsors

    Publication date:

    7/28/2016

    Effective date:

    7/28/2016

    POLICY

    A. Purpose

    As a federal contractor, Lawrence Berkeley National Laboratory (Berkeley Lab) is required to adhere to Department of Energy (DOE) Contract 31 regulations. This policy incorporates the requirements of the DOE Financial Management Handbook, Chapter 13, to ensure that sufficient advance funds be obtained from a non-federal sponsor prior to commencing work in order to maintain a positive cash balance during the life of the project.

    B. Persons Affected

    Any employee who manages payments for work performed for non-federal sponsor.

    C. Exceptions

    Exceptions to the advance requirement include state and local governments that are precluded by law from providing an advance. Small Business Innovative Research (SBIR) or Small Business Technology Transfer (STTR) sub-awards are also not subject to the standard advance requirement. Per DOE Financial Management Handbook, Chapter 13, SBIR/STTR sub-awards are only required to provide 30 days of advance funding. Non-SBIR/STTR projects that require an exception must be reviewed and approved by the Budget Office.

    D. Policy Statement

    To ensure a positive cash balance is maintained, the amount of the advance should be at least equal to the three highest months of estimated costs, including equipment and any other unusual start-up or operational costs, as represented in the total budget. An advance of the three highest months of estimated costs is based on Berkeley Lab's average accounts receivable aging for non-federal sponsors. A full advance is required for awards with a budget of $25,000 or less or that will be completed in 90 days or less. Methods for calculating the advance will vary depending on the type of work.

    Types of possible calculation methodologies include:

    1. Modified Straight-line: Advance = ((Total cost – start-up costs and/or large purchase) / Total number of months × 3) + start-up costs and/or large purchase
      1. Flat project burn rate with high start-up costs and/or a large purchase
        1. Example: Dr. Y is proposing work for Query Inc. for a total cost of $1,200,000. The project is anticipated to begin in September of 2010 and take 18 months to complete. Spending is expected to be about the same each month with the exception of an equipment purchase for $100,000 as well as $50,000 for supplies and materials in the first month.

          (($1,200,000 − $100,000 − $50,000) ⁄ 18 × 3) + $100,000 + $50,000 = $325,000

      2. Erratic burn rate where monthly projection of cost is unknown, with high start-up costs and/or a large purchase
        1. Example: Dr. Z is proposing work for the Air Society for a total cost of $1,725,000. The project is anticipated to begin in June of 2010 and take 24 months to complete. The monthly burn rate is expected to fluctuate throughout the life of the project, but a detailed cost plan has not been established. Initial supplies and materials total $100,000 as well as a large equipment purchase for $125,000.

          ($1,725,000 − $125,000 − $100,000) ⁄ 24 × 3) + $125,000 + $100,000 = $412,500

    2. Known Costing Profile: Advance = 1st highest month + 2nd highest month + 3rd highest month
      1. Erratic burn rate where monthly projection of cost is known (includes start-up costs and/or large purchases)
        1. Example: Dr. Q is proposing work for Money Trees Corp. for a total cost of $1,000,000. The project is anticipated to begin in December of 2010 and take 12 months to complete. Expected monthly spending is as follows per the detailed monthly spend forecast proposed to Money Trees Corp: December, $75,000; January, $94,000; February, $76,000; March, $78,500; April, $74,500; May, $79,000; June, $75,500; July, $157,000; August, $74,500; September, $74,000; October, $71,500; November, $70,500.

          $157,000 + $94,000 + $79,000 = $330,000  

    3. Unknown Costing Profile: Advance = Total cost ⁄ Total number of months × 3
      1. Flat project burn rate
        1. Example: Dr. W is proposing work for Global International for a total cost of $525,000. The project is anticipated to begin in October 2010 and take 12 months to complete. Spending is expected to be about the same each month.

          $525,000 ⁄ 12 × 3 = $131,330

      2. Erratic burn rate where monthly projection of cost is unknown, high start-up costs and/or large purchases are not expected
        1. Example: Dr. No is proposing work for Genes R Us Ltd. for a total cost of $1,325,000. The project is anticipated to begin in January 2010 and take 20 months to complete. It is not clear at this point what the monthly burn rate will be; high start-up costs are not expected, and the budget does not include large purchases

    $1,325,000 ⁄ 20 × 3 = $198,750

    E. Roles and Responsibilities

    Role

    Responsibilities

    Resource Analyst

    Works with the PI to determine the advance amount required

    IPO/RG Contract Officer

    Communicates and negotiates advance terms with sponsors

    Reimbursable Group

    Creates and distributes the advance invoice

    F. Definitions/Acronyms

    Term

    Definition

    Burn Rate

    The rate at which costs are incurred

    Strategic Partnership Projects (SPP)

    The performance of work for non-DOE entities by DOE/contractor personnel and/or the utilization of DOE facilities that are not directly funded by DOE appropriations

    G. Recordkeeping Requirements

    None

    H. Implementing Documents

    None

    I. Contact Information

    • Reimbursable Group Analyst
    • Reimbursable Group Manager

    J. Revision History

    Date

    Revision

    By whom

    Revision Description

    Section(s) affected

    Change Type

    7/28/2016

    1.2

    M. Fix

    Update for change from WFO to SPP; reduce advance requirements; clarify R&R

    All

    Minor

    3/25/2013

    1.1

    Franier

    Review completed 2/21/2013, no changes

    Pub & next review dates

    Minor

    1/2/2012

    1

    M. Mock

    Reformat for wiki

    All

    Minor

    DOCUMENT INFORMATION

    Title:

    Advance Payments for Sponsored Research Projects with Non-Federal Sponsors

    Document number

    11.02.010.000

    Revision number

    1.2

    Publication date:

    7/28/2016

    Effective date:

    7/28/2016

    Next review date:

    4/30/2018

    Policy Area:

    Budget

    RPM Section (home)

    Financial Management

    RPM Section (cross-reference)

    Section 11.15

    Functional Division

    OCFO

    Prior reference information (optional)

     

    Source Requirements Documents

    Other Driving Requirements

    Implementing Documents

    None

    • No labels

    Adaptavist ThemeBuilder EngineAtlassian Confluence