RPM | REQUIREMENTS AND POLICIES MANUAL

Viewable by the world

    Title:

    Capital Assets – Acquisition and Project Management

    Publication date:

    3/21/2023

    Effective date:

    3/21/2023

    BRIEF

    Policy Summary

    This policy provides directions on project management of capital-asset acquisitions (new construction projects such as additional or replacement buildings) implemented at Berkeley Lab. Berkeley Lab requires projects to be completed on schedule, within budget, and fully capable of meeting the Laboratory's mission performance, safeguards and security, and Environment, Safety & Health standards.

    Who Should Read This Policy

    This policy applies to facility and infrastructure projects implemented by Projects and Infrastructure Modernization Division (PIMD).

    To Read the Full Policy, Go To:

    The POLICY tab on this wiki page

    Contact Information

    Projects and Infrastructure Modernization Division

    Title:

    Capital Assets – Acquisition and Project Management

    Publication date:

    3/21/2023

    Effective date:

    3/21/2023

    POLICY

    A. Purpose

    This policy provides Projects and Infrastructure Modernization Division at Lawrence Berkeley National Laboratory (Berkeley Lab) with directions on project management of capital-asset acquisitions (new construction projects such as additional or replacement buildings). Berkeley Lab requires projects to be completed on schedule, within budget, and fully capable of meeting the Laboratory's mission performance, safeguards and security, and Environment, Safety & Health standards.

    B. Persons Affected

    This policy applies to Projects and Infrastructure Modernization Division employees who work on facility and infrastructure projects.

    C. Exceptions

    Not applicable

    D. Policy Statement

    All Projects and Infrastructure Modernization Division employees who work on construction projects will adhere to the Projects and Infrastructure Modernization Division Procedures Manual and, when applicable, DOE Directive 413.3B in order to provide mission-ready facilities for Berkeley Lab.

    E. Roles and Responsibilities

    Role

    Responsibilities

    Project Director/Manager

    • Adhering to the provisions of this policy
    • Overseeing every aspect of the project, from concept to launch, including transition to operations

    Project Controls Analyst

    • Adhering to the provisions of this policy
    • Maintaining financial/schedule and Earned Value Management System (EVMS) controls of the project

    Construction Manager

    • Adhering to the provisions of this policy
    • All field activities for building construction, including planning and incorporating safety

    Project Coordinator

    • Adhering to the provisions of this policy
    • All documentation coordination for the project

    F. Definitions/Acronyms

    Term

    Definition

    EVMS

    Earned Value Management System

    G. Recordkeeping Requirements

    Not applicable

    H. Implementing Documents

    Document number

    Title

    Type

    PIMD-PROC-001

    Projects and Infrastructure Modernization Division Procedures Manual

    Manual

    I. Contact Information

    Projects and Infrastructure Modernization Division

    J. Revision History

    Date

    Revision

    By whom

    Revision Description

    Section(s) affected

    Change Type

    1/2/2012

    0

    E. Tucker

    Rewrite for wiki

    All

    Minor

    1/14/2013

    1

    M. Smithwick

    Brief converted into a policy. Updated procedures manual and minor title corrections

    All

    Minor

    1/26/2015 1.1 J. Braithwaite Three-year review. E Minor
    3/21/2023 1.2 R. Sukhwani Periodic review: Clarified policy language. Updated Facilities Division to PIMD.  All Minor

    DOCUMENT INFORMATION

    Title:

    Capital Assets – Acquisition and Project Management

    Document number

    09.01.001.000

    Revision number

    1.2

    Publication date:

    3/21/2023

    Effective date:

    3/21/2023

    Next review date:

    3/21/2028

    Policy Area:

    Major Construction

    RPM Section (home)

    Facilities Management

    RPM Section (cross-reference)

    None

    Functional Division

    Projects and Infrastructure Modernization Division

    Prior reference information (optional)


    Source Requirements Documents

    DOE O 413.3B Chg 6 (LtdChg), Program and Project Management for the Acquisition of Capital Assets

    Implementing Documents

    Document number

    Title

    Type

    PIMD-PROC-001

    Projects and Infrastructure Modernization Division Procedures Manual

    Manual



    • No labels