July and August 2019 Electrical Shutdowns Planned

Electrical Shutdowns Planned

This is advance notice that Facilities is planning two electrical shutdowns for electrical distribution maintenance scheduled in July and August.  All power, except standby generator power, will be shut down to the affected buildings listed below. Facilities is providing this early notice so that Divisions can plan their research to minimize impacts to their science.

Electrical services, devices, and equipment connected to standby generator power will remain energized during the shutdown.  Please identify critical equipment that is not connected to standby generator power, that cannot remain off for 12 hours on a Saturday, and that is critical equipment requiring temporary generator power during this shutdown.  Please add temporary power needs to the links below in the following spreadsheets.

Utilities for Low Conductivity water (LCW) and Treated Water (TRW) will be shut down prior to the July outage as listed below.

Thank you for your cooperation and we will continue regular communications and assistance with you and your team leading up to this maintenance shutdown event.  Feel free to contact your respective Facility Area Manager with any questions.


Building Power Outage- SW-A4  Line 1

Saturday, July 13 from 5:00 AM to 5:00 PM

Buildings affected:

  • B2, B10A, B15, B23 (Guest House), B34, B37, and B43

Building impacts:

  • Stand-By Generator Power will be available
  • Outage conditions are not conducive to performing work
  • Restricted access to avoid workers in the labs without proper ventilation

Temporary Power Request Form




Low Conductivity Water (LCW NO FLOW) Shutdown

Thursday, July 11 at 3:00 PM – Tuesday, July 16 at 8:00 AM

Buildings affected:

  • B2, B6, B15, B27, B46, B53, B58, B58A, B80

Equipment affected:

  • All programmatic equipment currently cooled by LCW should be shut down.




Treated Water (TRW NO FLOW) Shutdown

Thursday, July 11 at 3:00 PM – Tuesday, July 16 at 8:00 AM

Buildings affected:

  • B2

B2 equipment affected:

  • Building Main Chillers- Office and Lab cooling will not be provided during the shutdown
  • AC Unit in B2-119
  • Process Cooling Chiller to 3rd Floor Laser Labs


Building Power Outage- SW-A4 Line 2

Saturday, August 10 from 5:00 AM to 5:00 PM

Buildings affected:

  • B17, B27, B30, B33, B33U, B47, B46, B53, B58, & B58A

Building impacts:

  • Stand-By Generator Power will be available
  • Outage conditions are not conducive to performing work