Lawrence Berkeley National Laboratory masthead LBNL Home A-Z Index U.S. Department of Energy logo Phone Book Jobs Search

Current and Planned Facilities Projects

New Construction Map
Project: B78 Roof replacement
Impact: Intermittent loss of parking at P lot
Dates: March - April 2017
PM: Dan Galvez
Project: Integrative Genomics Building
Impact:- Reduction of parking in Lot B1
-Increased car stacking
Dates: Current—End of FY19
PM: Jack Heffernan

Project: Modular Utility Plant
Impact: None
Dates: Current—End of FY18
PM: Jack Heffernan
Project: CRT Telecom Vault
Impact: Minimal, intermittent loss of parking around B59.
Dates: April 2017
PM: John Tully
Project: Old Town Demolition
Impact: Intermittent traffic; parking reduction for Segre Road, lots N1 & N3
Dates: Current – Summer 2017
PM: Ted Mankowski
Project: B37 Cooling Tower Replacement, Generator Replacement, Heat Exchanger Replacement
Impact: Intermittent traffic/parking reduction at Lawrence/Segre Roads
Dates: Current – Summer 2017
PM: Brian Taylor
Project: S Road Waterline Replacement
Impact: Intermittent traffic reductions (one-lane traffic) at S & Glaser Roads
Dates: April - June 2017
PM: Dan Galvez
Project: Roof Leak B-58
Impact: Water leaks could interrupt maintenance activities.
Dates: Current - September 30 2017
PM: Dave Cota
Project: B77A HVAC Replacement
Impact: Intermittent parking reduction for lot R, temporary power outages for 77A. Work restrictions likely in B77A during equipment lifts.
Dates: July - September 2017
PM: John Tully
Project: B83 Lab Upgrades
Impact: Electrical and IT outage localized to B83 likely. (B83 currently unoccupied.)
Dates: June - September 2017
PM: Susan McCutchan
Project: B46A Retaining Wall Replacement
Impact: Parking reduction for L lot; intermittent, localized site lighting outages to east side of B46.
Dates: July - August 2017
PM: Connie Lin
Project: B90 AC units replacement (roof)
Impact: Parking reduction for C lot, intermittent HVAC outages for 90. Work restrictions likely during equipment lifts.
Dates: May - June 2017
PM: John Tully
Project: Drai Flushing
Impact: Cafeteria sewers are being flushed this week. Possible water outage (minimal)
Dates: March 28 - April 3 2017
PM: Mike Elizalde
Project: Old Town Demolition
Impact: Intermittent parking reduction for Segre Road, lots N1 & N3
Dates: Current - Summer 2017
PM: Ted Mankowski
Project: Old Town Demolition
Impact: Parking Lot J closure; Lot I open during this time
Dates: April 6 - May 22, 2017
PM: Ted Mankowski
 

Click here to see typically not fully occupied parking areas

Adaptavist ThemeBuilder EngineAtlassian Confluence