Title: |
Permit to Penetrate Ground or Existing Surfaces |
Publication date: |
4/19/2022 |
Effective date: |
4/19/2022 |
BRIEF
Policy Summary
Berkeley Lab policy requires a permit to penetrate ground or existing surfaces (a dig permit) for all work requiring excavation, drilling, or driving of stakes or poles into the ground. A permit is also required to penetrate all existing concrete surfaces such as floor slabs, walls, beams, or columns.
A dig permit defines necessary steps for the safe penetration of ground, walls, or other existing surfaces on Berkeley Lab properties and addresses institutional requirements that must be completed before beginning any penetration work on any surfaces at Berkeley Lab.
Dig permits are issued by LBNL Facilities Utilities Coordinator or Utilities Section Manager the Berkeley Lab Utilities Engineer. Subcontractors may obtain a permit through the project manager.
Who Should Read This Policy
All subcontractors, Berkeley Lab employees, or affiliates who intend to penetrate any concrete or soil surface.
For More Details, Go To:
The POLICY tab on this wiki page
Contact Information
Utilities Coordinator
Facilities Division
Title: |
Permit to Penetrate Ground or Existing Surfaces |
Publication date: |
4/19/2022 |
Effective date: |
4/19/2022 |
POLICY
A. Purpose
The purpose of this policy is to summarize the requirements for a dig permit for anyone intending to penetrate the ground, walls, floors, beams, columns, or other existing surfaces at Lawrence Berkeley National Laboratory (Berkeley Lab). The permit defines the necessary steps for the safe penetration of ground or existing surfaces and addresses institutional requirements that must be completed before beginning any penetration work.
B. Persons Affected
All subcontractors, Berkeley Lab employees, or affiliates intending to penetrate concrete or soil surfaces.
C. Exceptions
- No dig permit is required for staking in soil no deeper than 6 inches using wood stakes.
- No dig permit is required for gypsum board (sheetrock) wall penetrations provided that the area has been swept for active and passive electrical current by the Berkeley Lab Utility Coordinator or designee. Both sides of the wall require visual inspection for evidence of repairs, and the wall cavity must be visually inspected for hidden objects. The wall cavity must be inspected by cutting a square opening (not more than a 10-inch square and not more than ¾ inch deep) and visually inspecting within the surface penetration area for any hidden objects. Multiple openings may be made for complete inspection of the wall cavity if needed.
- No dig permit is required for cutting asphalt berms provided the cut is less than 1⅝ inches into the underlying asphalt pavement.
- No dig permit is required for drilling into shielding blocks, however scanning of shielding blocks is required to avoid rebar.
D. Policy Statement
Before penetrating any surface at Berkeley Lab (ground, walls, floors, beams, columns, etc.), a dig permit must be requested and obtained. No work that requires a permit may begin until the permit is approved by LBNL Utilities Coordinator and Facilities Engineering Department and posted at the job site.
E. Procedure
- Subcontractor, or any other person, must request a dig permit at least ten (10) working days before beginning work to allow time for review and issuance of permit.
- Subcontractor must adhere to the conditions of the permit during work. The permit and all conditions in it are to be considered part of the work procedure and must be included in the subcontractor's bid package.
- In areas where a dig permit is not required, the subcontractor must verify by safe means, prior to drilling, that no utilities or services are within the area to be drilled.
- A dig permit is required for all concrete surface penetration work regardless of depth (walls, floors, and ground—including asphalt paving, etc.). For other types of penetrations, this permit is required if the penetration depth is greater than 1⅝ inches.
- A dig permit will not be issued if the area cannot be scanned or reliable data on utilities location cannot be obtained.
- The permit is valid for 45 calendar days from the time of issuance. One 45-day extension may be requested.
F. Roles and Responsibilities
Role |
Responsibility |
Subcontractor or Person Requiring a Permit to Penetrate |
|
Facilities Project Manager/Construction Manager |
|
Dig Permit Office |
Thoroughly inspects areas that require penetration, and issues a set of conditions, if necessary |
Utility Coordinator |
Sweeps areas for active and passive electrical currents |
G. Definitions/Acronyms
Term |
Definition |
Penetration |
Any action that punctures existing surfaces |
Surface |
Physical element including ground, walls, floor, beams, columns, etc. |
H. Recordkeeping Requirements
Issuance of a dig permit to penetrate ground or existing surfaces of Berkeley Lab property
I. Implementing Documents
Document Number |
Other Reference |
Title |
Type |
ADMN-053 |
Procedure |
||
07.07.006.004 |
PUB-3000, Ch. 34, Work Process C |
Process |
J. Contact Information
Utilities Coordinator
Facilities Division
K. Revision History
Date |
Revision |
By whom |
Revision Description |
Section(s) affected |
Change Type |
4/19/2022 | 2 | E. Lahrs | Periodic review: minor policy changes to align with current permit procedures. Contact info and R&R updates. | All | Minor |
6/27/2012 |
1 |
E. Tucker |
Rewrite for wiki |
All |
Minor |
1/2/2012 |
0 |
E. Tucker |
Rewrite for wiki |
All |
Minor |
DOCUMENT INFORMATION
Title: |
Permit to Penetrate Ground or Existing Surfaces |
Document number |
09.04.001.000 |
Revision number |
2 |
Publication date: |
4/19/2022 |
Effective date: |
4/19/2022 |
Next review date: |
4/19/2027 |
Policy Area: |
Utilities |
RPM Section (home) |
Facilities Management |
RPM Section (cross-reference) |
none |
Functional Division |
Facilities |
Prior reference information (optional) |
Source Requirements Documents
- DOE Order 430.1C, Change 2, Real Property Asset Management
Other Driving Requirements
- ES&H Core Policy, 07.01.001.000
Implementing Documents
Document Number |
Other Reference |
Title |
Type |
ADMN-053 |
Procedure |
||
07.07.006.004 |
PUB-3000, Ch. 34, Work Process C |
Process |