Title: |
Audit Resolution and Follow-up |
Publication date: |
8/8/2022 |
Effective date: |
8/8/2022 |
BRIEF
Policy Summary
This policy defines the requirements and responsibilities for reporting, tracking, resolution, and closure of all audit findings, observations, and recommendations (internal and external), as appropriate, at Lawrence Berkeley National Laboratory (Berkeley Lab). Berkeley Lab management must ensure appropriate corrective actions are implemented to resolve and complete audit findings and recommendations in accordance with established target due dates.
Who Should Read This Policy
All employees responsible for Berkeley Lab audit-related activities, including corrective actions (internal and/or external)
To Read the Full Policy, Go To:
The POLICY tab on this wiki page
Contact Information
Title: |
Audit Resolution and Follow-up |
Publication date: |
8/8/2022 |
Effective date: |
8/8/2022 |
POLICY
A. Purpose
This policy defines the requirements and responsibilities for reporting, tracking, resolution, and closure of all audit findings and recommendations (internal and external) at Lawrence Berkeley National Laboratory (Berkeley Lab).
B. Persons Affected
Any employee responsible for Berkeley Lab audit-related activities, including corrective actions (internal and/or external)
C. Exceptions
None
D. Policy Statement
1. General
Audits, including inspections, investigations, and advisory reviews, are management tools used to detect fraud, waste, and abuse; validate program compliance, internal controls, and financial position; and promote effective risk management. Audit resolution, closure, and follow-up are critical to ensure that Berkeley Lab continuously employs best practices and complies with Department of Energy (DOE) Contract 31 and University of California (UC) directives. Berkeley Lab management must ensure appropriate corrective actions are implemented to resolve and complete audit findings, observations, and recommendations, as appropriate, in accordance with established target due dates. Drafts of internal and external audit reports are typically issued for management review and comment. When appropriate, management must submit its formal responses on findings and recommendations to the originating audit agency or department in accordance with an established due date. The response must include a targeted completion date for any findings or recommendations that warrant corrective actions. Targeted completion dates should be realistic and achievable. The Laboratory will track corrective actions in accordance with the standards set forth by the Laboratory's Office of Institutional Assurance and Integrity. This includes identifying, recording, and managing audit recommendations and associated corrective actions from inception through resolution in the Berkeley Lab Corrective Action Tracking System (CATS). In addition, IAS will independently track all internal audit findings and recommendations and coordinate follow-up on external audit findings and recommendations as required by UC policy and business practice.
2. Corrective Action Resolution and Closure
A distinction is made between the closure and resolution of corrective actions (see Glossary).
- Closure: Closure occurs when the proposed corrective actions are completed and concurrence is obtained from the originating audit agency or department. Closure of external audits should generally take no longer than one year after issuance of the final report. Closures scheduled to take longer than one year require a written justification submitted to DOE and entered into DARTS.
- Resolution:
- Office of Inspector General (OIG) Audits: For audits and inspections conducted by the DOE OIG, resolution occurs when DOE management and the OIG agree on corrective actions to be taken on reported findings and recommendations. Resolution shall be made within a maximum of six months after issuance of a final report; see Office of Management and Budget (OMB) Circular A-50, Paragraph 8.b. (2).
- Government Accountability Office (GAO): Resolution is defined as the point at which the audit organization and agency management or contracting officials agree on actions to be taken on reported findings and recommendations; or, in the event of disagreement, the point at which the audit follow-up official determines the matter to be resolved; see OMB Circular A-50, Paragraphs 6.b.
E. Roles and Responsibilities
Role |
Responsibility |
|
|
Internal Audit Services |
|
LBNL Audit Advisory Committee |
|
Office of Institutional Assurance and Integrity |
Manages and maintains CATS to track corrective actions and analyze trends resulting from assessments and/or inspections. |
F. Definitions/Acronyms
Term |
Definition |
Audit Closure |
The proposed corrective actions of the audit are completed and the auditor agrees that actions taken satisfactorily address the deficiency identified. Closure of external audits should generally take no longer than one year after issuance of the final report. Exceptions require a written justification be submitted to DOE, entered in DARTS, and be subject to audit. |
Audit Finding |
A program or performance deficiency where there is a noncompliance with an established external or internal requirement. It is a generic term used to refer to programmatic or performance deficiencies, nonconformances, regulatory or procedural noncompliances, procedure inadequacies, assessment findings, external oversight findings, and associated actions that require formal corrective action. This includes but is not limited to a failure, defect, deviation, malfunction, deficiency, or nonconformance of plant equipment, materials, or procedures; or personnel safety concerns or events that have or could have an effect on the safe, reliable, or efficient operation of the Laboratory, or which involve a failure to be in compliance with requirements. |
Audit Observation | A practice or condition that is not technically noncompliant with an external or internal regulation or requirement, but could lead to noncompliance if left unaddressed. |
Audit Observation |
A practice or condition that is not technically noncompliant with an external or internal regulation or requirement, but could lead to noncompliance if left unaddressed. |
Audit Recommendation |
Auditor-suggested course of action to address issues, concerns, deficiencies, and improvements described in the audit finding or observation. |
Audit Resolution |
An agreement between the primary organization (auditee) and the auditor on corrective actions to be taken for audit findings and recommendations (i.e., management concurs with the findings and recommendations, or a management decision is issued indicating concurrence and expected completion dates). |
Audit Response |
A written comment by management indicating agreement or disagreement on reported findings and recommendations. Comments indicating agreement on draft reports must include planned corrective actions and dates for achieving such actions. Comments indicating disagreement should fully explain the reason(s) for disagreement. Disagreements on internal audit findings and recommendations should be resolved before issuance of the final report. |
Corrective Action |
An action that addresses a deficiency and/or the cause of an issue or audit finding and prevents or significantly reduces the likelihood of the same problem occurring again |
G. Recordkeeping Requirements
None
H. Implementing Documents
Document Number |
Title |
Type |
PUB-5519(1) |
Manual |
I. Contact Information
J. Revision History
Date |
Revision |
By Whom |
Revision Description |
Section(s) Affected |
Change Type |
8/8/2022 | 4 | A. Flores | Periodic review: minor updates on the resolution process, R&Rs and SRDs. | D.1.2; E; SRDs | Minor |
12/17/2020 | D. Soustin | Updated Contract 31 I clause numbers as per mod 1105 | Source Requirement Documents | Editorial | |
6/1/2019 |
3 |
T. Carlson/A. Flores |
Revise policy to have institutional focus (not just financial); remove process info |
All |
Major |
5/22/2012 |
2 |
M. Mock |
Updates to policy |
A, D, E, F, H, I |
Minor |
1/2/2012 |
1 |
M. Mock |
Re-format for wiki |
All |
Minor |
DOCUMENT INFORMATION
Title: |
Audit Resolution and Follow-up |
Document number |
11.07.003.000 |
Revision number |
4 |
Publication date: |
8/8/2022 |
Effective date: |
8/8/2022 |
Next review date: |
8/8/2027 |
Policy Area: |
Financial General Policies and Information |
RPM Section (home) |
Financial Management |
RPM Section (cross-reference) |
Section 11.18 |
Functional Division |
Internal Audit |
Prior reference information (optional) |
RPM Section 11.18 |
Source Requirements Documents
- Contract 31, Clause I.149. DEAR 970.5232-3, Accounts, Records and Inspection (DEC 2010) (prev. I.103)
- DOE Order 224.3A, Auditing of Programs and Operations
- Office of Management and Budget (OMB) Circular A-50, Paragraph 8.a (2), Paragraphs 6.b(3) and 8.b(4)
- International Standards for the Professional Practice of Internal Auditing
- Issues Management Policy
Implementing Documents
Document Number |
Title |
Type |
PUB-5519(1) |
Manual |