Viewable by the world


Project reports provide written documentation as necessary showing the scope, schedule, and cost of the project, as of the date of the report. As a result, major unresolved problems can be identified. Various project reports are developed during the month to communicate the technical, cost, and schedule performance of each project. For less complex projects, reporting requirements may include:

Report Title

Description and Content

Developed by

Timetable

Project Cost Plan

An Excel spreadsheet that tracks time-phased budget funding and actuals by WBS/Project ID.

Project Manager/Project Coordinator

Second week of each month

Detail Schedule

Developed in MS Project by WBS. Contains schedule performance by planned vs. actual schedule.

Project Manager/Project Controls

First week of each month, or as needed

Project Change Log

Documents project changes, associated costs, and Project Director review of changes.

Project Manager/Project Coordinator

As needed to remain current

GPP Financial Status Report

List of GPP/IGPP projects, showing Total Estimated Cost, costs, funding, project phase, and noteworthy information.

Resource Analyst/Project Manager

Second week of each month

Risk Register

An Excel spreadsheet that captures project risks, probabilities, and impacts.

Project Manager

Monthly

For more complex projects, reporting requirements may include:

6.13.1      Monthly and Quarterly Status Reports

  • The Project Manager is responsible for the accuracy of project reports. The Office of the Chief Financial Officer is responsible for assurance review of the financial information. Project reports will be prepared with support from the project team and issued on a monthly or quarterly basis. The cost of preparing project reports will be charged to the project.
  • Project status reports will follow the agreed upon content, format, and timing of the DCM suite of reports unless agreed otherwise by the DCM Department Manager. Additional reports required by the client, LBNL management, or government agencies will be prepared and submitted as required. Such reports will be consistent with the information presented in the standard status reports.
  • Project Managers will notify the Project Director, project sponsors, project initiators, or other interested managers that a problem exists as part of the day-to-day management of the project. As a result, the responsible senior managers will have been notified of major problems before they receive a report displaying unresolved variances and problems. A project status report will not be used to notify these managers that a major project problem exists for the first time.
  • The information presented in the status reports should be succinct enough to highlight the project status, summarize project issues, and identify project risks. Detailed project information should be described in supporting documents.
  • For projects performed at leased facilities, all construction costs shall be tracked and reported separately from lease costs.  In order to provide proper accounting and capitalization, construction costs should use a Facilities Project I.D. that is not parented to the lease expense account. Construction costs paid for by third parties (such as a landlord tenant improvement allowance) shall be reported if it will provide a more accurate representation of the project and such information is meaningful to users of the report. Reports should clearly state if third party costs are included so that the information is not misleading.

6.13.2      Reporting Requirements

Each capital project managed through the Facilities Division will use best project management practices and principles. When applicable, this will include complying with DOE Order 413.3B, Program and Project Management for the Acquisition of Capital Assets, and LBNL’s Earned Value Management System (EVMS) Procedures to track and report project performance.

Due to the various types, sizes, complexities, and funding sources of each project, not all projects managed by DCM are required to comply with DOE Order 413.3B. A modified EVMS approach may be implemented in such cases.

The monthly reports shall clearly communicate the following data:

  • Scope, schedule, and budget performance (non-EVMS projects)
  • EVMS data and performance (if required)
  • Current milestone status
  • Current issues and risk areas, including proposed corrective actions
  • Baseline changes
  • Status date of the project information and accounting close date for financial data

The table below represents the current set of reports developed in support of DCM. Various project reports are developed during the month to communicate the technical, cost, and schedule performance of each project, and may include:

Report Title

Description and Content

Developed by

Timetable

Project Cost

An Excel spreadsheet that tracks

Project

Second Monday

Sheet

time-phased budget funding and

Coordinator/

of each month

actuals by WBS/Project ID.

Project

Manager

Detail Schedule

Developed in P3e by WBS. Contains schedule performance against planned versus actual schedule.

Project Controls

First week of each month

EVMS Reports

Specific requirements defined under DOE Order 413.3B to include at a minimum a Cost Performance Report.

Project Controls

Completed and finalized by third Thursday of each month

FacilitiesProjectsList

List of active Facilities Projects, showing Total Estimated Cost, costs, funding, performance stop light, and noteworthy information.

Resource Analyst

Second Friday of each month

GPP Financial Status Report

List of GPP/IGPP projects, showing Total Estimated Cost, costs, funding, project phase, and noteworthy information.

Resource Analyst/ Project Manager

BeforesecondFriday of each month

Overhead Budget Status Report

Status of DCM overhead budgets vs. actuals, liens, and remaining funding.

Resource Analyst

By 15th of each month

DOE Monthly Status Reports

Summarizes monthly scope, schedule, and cost performance for Line Item Projects.

Project Manager

BeforethirdThursday of each month

DOE Quarterly Status Reports

Summarizes quarterly scope, schedule, and cost performance for Line Item Projects.

Project Manager

BeforethirdThursday of each quarter (Jan., April, July, Oct.)

Facilities Division Spend Plan

This document shows the Facilities Division Spend Plan and Forecast.

Resource Analyst

A minimum of four times per year

Risk Registry

An Excel spreadsheet that captures project risks, probabilities, and impacts.Basisfor Monte Carlo risk simulations.

Project Coordinator

Monthly

Capital Projects Update

High-level project status presentation to Operations group.

Project Manager

First Monday of each month