  • The Project Manager or designated Architect/Engineer shall review Requests for Information (RFIs) from the construction subcontractor and provide a response, with copies to the appropriate project team members. A/E of record and the construction inspector must be copied on all RFI responses.
  • The Project Manager/Project Coordinator shall route design clarification RFIs to the A/E of record for response.
  • The Project Coordinator shall maintain an RFI Log, using the standard format, including the date they were received from the subcontractor and the date a response was sent to the subcontractor.