Clause in CRD

Implemenentation

Regardless of the performer of the work, the contractor is responsible for compliance with the provisions and requirements of this CRD and flowing down CRD requirements to subcontractors at any tier to ensure the contractor’s compliance with these provisions and requirements. As directed by the contracting officer, the contractor must meet the following requirements.

N/A Boilerplate

The contractor must implement and comply with the applicable Program Cyber Security Plan (PCSP), as provided by Senior DOE Management, for all cyber security activities involving unclassified or national security information systems; compliance with the PCSP is monitored by Senior DOE Management.

The applicable PCSP as of the inclusion of this clause is the March 2, 2007 Version.  BSO and LBL have agreed in writing that the current version of the ATO (Computer Security Program Plan) as approved by the BSO constitutes the acceptable set of deviations from the PCSP.  See letter from Adam Stone to Rodney Royster July 23, 2009.

  • No labels