5.7.1 Receipt Inspection Process

The following describes the material receipt inspection process for the LBNL project team and construction subcontractors.  All material to be used on a project shall be inspected using a risk based approach, with high risk materials receiving a more rigorous review.  Material delivered should be previously approved by the Registered Design Professional and LBNL Facilities Engineering via the subcontractor submittal process.

Subcontractor shall establish a LBNL project team-approved staging area (lay down area) for all materials received.  For projects that cannot accommodate a laydown area, project team and subcontractors will establish an alternate location (e.g., subcontractor truck, warehouse, etc.).

  1. Subcontractor coordinates receipt and placement of all materials to ensure they are properly staged.
  2. Subcontractor inspects all materials to ensure that they are consistent with the approved submittal and subcontract requirements.  Subcontractor shall promptly remove from the jobsite all materials that do not meet approved submittal and subcontract requirements to ensure that they are not installed.
  3. After subcontractor inspection, the subcontractor notifies LBNL’s Construction Manager to inspect the material.  The Construction Manager or his representative coordinates LBNL project team inspections and should, if possible, include all LBNL parties concurrently to avoid redundant inspections.
  4. LBNL project team reviews the approved submittal and any previously approved substitution from LBNL specifications.  Project Manager is responsible for ensuring the project team receives the approved submittal(s).
  5. LBNL project team inspects staged materials to ensure that they are compliant with the approved submittal, LBNL technical specifications, and other applicable subcontract requirements.

5.7.2 Suspect/Counterfeit Items

A suspect item is one in which there is an indication by visual inspection, testing, or other information that it may not conform to established government or industry-accepted specifications or national consensus standards.  A counterfeit item is a suspect item that is a copy or substitute without legal right or authority to do so, or one whose material, performance, or characteristics are knowingly misrepresented by the vendor, supplier, distributor, or manufacturer.  (Refer to “LBNL Suspect Counterfeit Items (S/CI)” webpage for additional guidance:  https://commons.lbl.gov/pages/viewpage.action?pageId=118587972.)

The range of items at LBNL that should be considered as possible Suspect/Counterfeit Items includes the following:

DOE maintains a list of Suspect/Counterfeit Items and identification guidance on the DOE web site at http://www.sci.doe.gov.

Contact the Office of Institutional Assurance and Integrity if construction materials are found on site with the following characteristics:

Foreign made items identified in the contract or approved in the Procurement variance process are not subject to these requirements.  NRTL stamped/marked assemblies/systems are not required to have each individual component inspected.

The Project Manager shall promptly inform, via direct contact, Facilities line management (Project Director, DCM Department Head, and the Facilities Division Deputy Director), the Office of Institutional Assurance & Integrity, and the EHS Team Lead of any Suspect/Counterfeit Items identified on a project.  The presence of a Suspect/Counterfeit Item on a project may require a DOE Occurrence Report (refer to LBNL PUB‑3000, Chapter 15, and PUB‑3111, Chapter 2.3.3, "Nonconforming and Suspect/Counterfeit Items", for requirements).

To Help Expedite A&I Determinations, send photos of the entire product, the certificate of conformance, and specifically the markings or areas that are potentially suspect.  Also send copies of the packing slip, inspection report, and certificates of conformance for product.