Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.
  1. RF power levels and waveforms of all signals provided at cable output in the racks
  2. Amplitude and phase stability of the S-band RF at the output of the LINAC (Accelerating Section 2)RF system and components - intra pulse and inter pulse
  3. Latency breakdown

RF Power Levels

  • All data stored here
  • Time estimate - request 4 hrs for margin
    • Peak power measurements: 0.5 hr
    • Scope measurement:
      • Validate trigger: 0.5 hr
      • Waveform alignment: 0.5 hr
      • Take data, moving cart with scope around, capturing overlays: 1 hr
        • TODO: add desired timing overlay captures
    • Restore all cables and confirm normal operation
  • TODO: confirm all cables installed; has cable 107 been replaced?

...