LBLnet Recently Completed Projects

  • ALS User Services Building Network - FY10

  • ALS User Services Building Server Room Network - FY10

    ALS User Services Building Network - FY10

    LBLnet engineers will install network equipment in the new ALS User Services Building in this project.

    TaskStatusScheduled Start DateScheduled Completion DateCompletion Date
    Plan, design, and procurementIn progressMarch 1, 2010May 26, 2010
    Optical fiber orderNot startedMay 17, 2010May 17, 2010
    Network equipment installationNot startedMay 25, 2010June 16, 2010
    Wireless network equipment installationNot startedMay 25, 2010June 14, 2010
    DocumentationNot startedJune 15, 2010June 15, 2010

    ALS User Services Building Server Room Network - FY10

    LBLnet engineers will install network equipment in the ALS User Services Building server room in this project.

    TaskStatusScheduled Start DateScheduled Completion DateCompletion Date
    Plan, design, and procurementIn progressMarch 26, 2010June 29, 2010
    Optical fiber installation and testingNot startedMay 3, 2010July 6, 2010
    Network equipment installationNot startedJuly 6, 2010July 20, 2010
    Testing and documentationNot startedJuly 21, 2010August 9, 2010