All Completed Projects

Skip to end of metadata
Go to start of metadata

Previous LBLnet Projects

  • ALS Beamline upgrades - FY10

  • End of Life (EOL) Switch Replacements - FY10

  • LBLnet Equipment Rack Replacements - FY10

    Recently Completed LBLnet Projects

  • End of Life (EOL) Switch Replacements - FY09

  • End of Life (EOL) Switch Replacements - Phase II Planning

  • Wireless Access Point Installations - Planning.

  • Enable Employee and Visitor Networks on All Wireless Access Points.

    ALS Beamline upgrades - FY10

    LBLnet engineers will replace Cisco fast Ethernet (10/100) switches with gigabit Ethernet (10/100/1000) switches in this project.

    BeamlineSubnetStatusScheduled DateCompletion Date *
    BL8131.243.74Scheduled for installation April 26, 2010June 1, 2010
    BL8131.243.81Scheduled for installation April 26, 2010May 26, 2010
    BL7131.243.73Scheduled for installation May 11, 2010June 1, 2010
    BL9131.243.75Scheduled for installation May 11, 2010May 26, 2010
    BL6131.243.72Scheduled for installation June 1, 2010May 11, 2010
    BL5131.243.79 Scheduled for installation June 1, 2010June 1, 2010
    BL5131.243.80 Scheduled for installation June 1, 2010June 1, 2010
    BL4131.243.83Scheduled for installation June 1, 2010May 26, 2010
    BL3131.243.82Scheduled for installation June 2, 2010May 11, 2010
    BL2131.243.91Scheduled for installation June 3, 2010May 11, 2010
    * Note: These dates are subject to change due to ALS maintenance scheduling requirements.

    LBL EOL Switch Replacement Project - FY10

    LBLnet engineers will replace End of Life Cisco and Force10 switches in this project.

    BuildingSubnetStatusScheduled DateCompletion Date
    50A131.243.129Scheduled for installationMay 11, 2010Re-visit
    77128.3.48Scheduled for installationMay 18, 2010May 20, 2010
    90R128.3.76Replaced defective hardwareNot ScheduledMay 19, 2010
    62131.243.12Scheduled for installation May 24, 2010June 16, 2010
    25A128.3.132Scheduled for installationMay 25, 2010May 18, 2010
    70131.243.28Scheduled for installationMay 25, 2010June 17, 2010
    50A131.243.112Scheduled for installationJune 7, 2010August 10, 2010
    47128.3.128Scheduled for installation June 14, 2010Re-visit
    50A128.3.5Scheduled for installationJune 21, 2010June 21, 2010
    88 Basement128.3.32Scheduled for installation June 28, 2010Re-visit
    1 (Donner)131.243.32Scheduled for installation July 12, 2010Re-visit
    90128.3.12 & 128.3.20Scheduled for installation July 24, 2010August 7, 2010
    90C128.3.76Scheduled for installationJuly 31, 2010May 18, 2010
    72131.243.3Scheduled for installationAugust 3, 2010May 18, 2010
    70 Annex131.243.28Scheduled for installationAugust 10, 2010May 26, 2010

    LBLnet Equipment Rack Replacements - FY10

    LBLnet engineers will install and populate new network equipment racks in the central telecommunications room in this project.

    TaskStatusScheduled Start DateScheduled Completion DateCompletion Date
    Plan, design, and procurementIn progressMarch 25, 2010April 7, 2010
    Rack N08 (core switch)Not startedApril 5, 2010April 7, 2010April 6, 2010
    Rack N07 (wireless)Not startedApril 19, 2010April 30, 2010
    Rack N06 (VPN, firewalls)Not startedApril 28, 2010May 18, 2010
    Rack N05 (taps, point-to-point)Not startedMay 10, 2010May 24, 2010
    Rack N04-N01 (subnet switches)Not startedJune 4, 2010June 28, 2010



    LBL EOL Switch Replacement Project - FY09

    LBLnet engineers will replace End of Life Catalyst 4000 series switches in this project.

    Equipment was received late.

    BuildingSubnetStatusScheduled DateCompletion Date
    76131.243.96Scheduled for installation March 10, 2009March 10, 2009
    50A128.3.5Scheduled for installation March 11, 2009July 9, 2009
    70A128.3.180Scheduled for installation March 13, 2009March 13, 2009
    55131.243.10Scheduled for installation March 17, 2009March 17, 2009
    1131.243.32-35Third floor switch scheduled for installation March 18, 2009Used in 46-232C
    50131.243.48Scheduled for installation March 19, 2009March 26, 2009
    1131.243.32-35Fourth floor switch scheduled for installation September 22, 2009October 1, 2009
    72131.243.3Scheduled for installation April 21, 2009June 30, 2009
    977128.3.60-63Scheduled for installation May 5, 2009Re-visit
    70131.243.28-31Scheduled for installation May 27, 2009Cancelled for cost
    66131.243.16-19Scheduled for installation June 30, 2009July 2, 2009
    88128.3.32-35 and 128.3.252-255Scheduled for installation July 28, 2009March 16, 2009
    88128.3.32-35 and 128.3.252-255BasementCloset space issue
    71131.243.168-169Scheduled for installation July 7, 2009July 7, 2009
    26131.243.210Scheduled for installation July 7, 2009July 7, 2009



    LBL EOL Switch Replacement Project - Phase II

    LBLnet engineers will replace End of Life Catalyst 5000 series switches in this project.

    BuildingSubnetStatusScheduled DateCompletion Date
    69131.243.172completedApril 24, 2008April 24, 2008
    50B128.3.10-11completedMay 21, 2008May 21, 2008
    46128.3.128-131completedJune 12, 2008June 12, 2008
    50B128.3.2completedAugust 21, 2008August 15, 2008
    65128.3.32-35completedAugust 21, 2008August 15, 2008
    51131.243.36Scheduled for removal from serviceFebruary 28, 2009Still needed for security webcam
    76131.243.96-99Waiting on completion of constructionFebruary 6, 2009February 26, 2009



    LBL Wireless Access Point Installations

    LBLnet is planning the installation of 58 more wireless access points by the end of Q1 2009.

    BuildingStatusScheduled DateCompletion Date
    9779 APs completedAugust 22, 2008August 22, 2008
    13 APs completedSeptember 19, 2008October 31, 2008
    42 APs completedSeptember 19, 2008September 19, 2008
    52 APs completedSeptember 19, 2008September 19, 2008
    161 AP completedSeptember 19, 2008September 19, 2008
    906 APs completedNovember 21, 2008December 3, 2008
    625 APs completedDecember 12, 2008December 12, 2008
    646 APs completedDecember 19, 2008December 19, 2008
    665 APs completedJanuary 9, 2009January 9, 2009
    693 APs completedJanuary 16, 2009January 16, 2009
    70A2 APs completedJanuary 23, 2009January 21, 2009
    831 AP completedJanuary 30, 2009January 28, 2009
    714 APs completedFebruary 6, 2009February 6, 2009
    763 APs completedFebruary 13, 2009February 13, 2009
    846 APs completedFebruary 27, 2009March 4, 2009



    Availability of Employee and Visitor Networks on All Wireless Access Points

    Our long term plan is to make the Employee and Visitor networks available everywhere we provide wireless service by July 2009, pending funding. Individual conversions will be made as needed. Schedule



    LBLnet Services Group :: LBLnet Projects Completed

  • 10 Gigabit Ethernet Upgrades.

  • Building 90 Subnet Split.

  • Deploy CPP Linksys network monitors on LBLnet.

  • Switch upgrades for IT Infrastructure subnets.

  • End of Life (EOL) Switch Replacements - Phase I

  • Wireless Access Point Upgrades

  • JGI Network Upgrade



    LBL 10 Gigabit Ethernet Upgrade PHASE II

    Phase II of the 10 Gigabit Ethernet Upgrade project is complete. LBLnet core routers have been connected to the core switch at 10Gb/s. Subnets have been moved from existing routers to 10G-connected routers as scheduled. Schedule




    LBL EOL Switch Replacement Project - Phase I Complete, 22 August 2007

    Building(s)
    Subnet
    Status
    Date
    7
    131.243.96 - 131.243.99
    completeAugust 2, 2007
    27, 53, 75, 75A, 75B
    131.243.208 - 131.243.211
    completeAugust 2, 2007
    48, 85, 85B
    131.243.248
    completeAugust 2, 2007
    4, 5, 25A, 41, 44B
    128.3.2
    complete August 2, 2007
    50B
    128.3.10 - 128.3.11
    completeAugust 6, 2007
    50B
    128.3.2
    completeAugust 6, 2007
    27, 53
    131.243.208 - 131.243.211
    completeAugust 21, 2007
    14
    131.243.120
    completeAugust 21, 2007
    25
    128.3.132
    completeAugust 21, 2007
    85
    131.243.248
    completeAugust 21, 2007
    54
    131.243.160 - 131.243.163
    completeAugust 21, 2007
    74
    131.243.224 - 131.243.227
    completeAugust 22, 2007
    31
    128.3.48
    completeAugust 22, 2007
    48
    131.243.248
    completeAugust 22, 2007
    71
    131.243.168 - 131.243.171
    completeAugust 22, 2007



    LBL Wireless Access Point Conversion: COMPLETE, 13 September, 2007

    CPP has funded upgrades to replace first- and second-generation Orinoco Wireless Access Points.

    All 66 Orinoco APs have been converted to the new Cisco Access Points.


    LBL Switch upgrades for IT Infrastructure subnets

    Switch upgrades for 128.3.41, 127.3.72, and 128.3.60 subnets are in progress. .

    SubnetStatusScheduled DateCompletion Date
    128.3.41upgrade completeJune 8, 2008June 8, 2008
    131.243.60upgrade completeJune 24, 2008June 24, 2008
    131.243.72upgrade completeMay 20, 2008May 20, 2008


    Building 90 Subnet Split

    Separation of the 128.3.12 and 128.3.20 subnets in building 90 will improve performance and increase the number of IP addresses available. This is the final phase of infrastructure upgrades in building 90. New hardware has been installed, including a 10 gigabit Ethernet intra-building backbone. This project was completed on July 1, 2008



    Deploy CPP Linksys network monitors on LBLnet

    CPP has developed network monitoring devices using low-cost Linksys routers. These monitors are being deployed weekly. 88 of 103 monitors have been installed. This project was completed on July 2, 2008.



    JGI Network Upgrade

    New sequencers and storage systems will be installed in buildings 100 and 400 respectively, increasing the demand for bandwidth between the 198.129.88 and 198.129.90 subnets. The first phase of the upgrade is to replace the core router, 198.129.88 and 198.129.90 subnet switches with new equipment and provision the links using 10 Gigabit Ethernet. The scheduled completion date for this phase of the project is July 15, 2008. Project completed on July 5th, 2008.

    • No labels